Surrey, BC Guaranteed Permitting Timelines program brings greater certainty to permit process
Surrey, BC Guaranteed Permitting Timelines Certainty Process
В процес на изпълнение
Rezoning permits previously lacking guaranteed dates are now processed in 12 weeks for single-family properties. This initiative created a 16-week timeline for multi-family, industrial, and rezoning projects. Surrey City Council also solidified existing 10-week timelines for single-family and tenant-improvement permits. City officials expedite completed permit applications with extended office hours, streamlined reviews, and an expanded permit portal.
Успешен Проект
Surrey processed permits within established timelines in three of four categories in the program's first six months.