Surrey, BC Guaranteed Permitting Timelines program brings greater certainty to permit process

Surrey, BC Guaranteed Permitting Timelines Certainty Process

In Progress

Rezoning permits previously lacking guaranteed dates are now processed in 12 weeks for single-family properties. This initiative created a 16-week timeline for multi-family, industrial, and rezoning projects. Surrey City Council also solidified existing 10-week timelines for single-family and tenant-improvement permits. City officials expedite completed permit applications with extended office hours, streamlined reviews, and an expanded permit portal.

SB

Surrey, BC

City in British Columbia

CA flag

Canada

Newsworthy

GP

Guaranteed Permitting Timelines Initiative Accelerating Processing of Building Permitting in Surrey | City of Surrey

The latest data collected shows significant process on the City of Surrey’s Guaranteed Permitting Timelines.

CS

Council Streamlines Development Permit Process by Approving Guaranteed Timelines | City of Surrey

Council streamlines development permit process by approving guaranteed timelines for building and rezoning permits

Project Succeeded

Surrey processed permits within established timelines in three of four categories in the program's first six months.

Related Projects

Cincinnati, OH to repurpose vacant downtown office buildings into residential units
Calgary, AB and Edmonton develop carbon-neutral construction practices with ENBIX initiative

🚫 To join the discussion, sign up. It's free!

  • About
  • Advertise
  • Help
  • Blog
  • Terms of Service
  • Privacy
  • Cookie Policy
  • Contact

© 2024 Govlaunch Inc.